Skip to main content

Table 24 Ranking of alternatives in Economic criterion

From: Application of the transdisciplinary shipyard energy management framework by employing a fuzzy multiple attribute group decision making technique toward a sustainable shipyard: case study for a Bangladeshi shipyard

Alternatives

Ci*

Rank

E1 = Financial source

0.5944

4

E2 = Levelized cost of energy (LCOE)

0.6875

2

E3 = Life cycle cost (LCC)

0.6459

3

E4 = Societal cost

0.3876

7

E5 = Cost benefit analysis (CBA)

0.6947

1

E6 = Competitiveness

0.4687

6

E7 = Incentive regime

0.4735

5